The progress of urban train projects have not met public expectation, said Deputy PM Hoang Trung Hai during a recent meeting to review the progress of urban train projects in Hanoi and HCM City.
The construction of the Hanoi Urban Railway Project in Cau Dien (Photo: VNA)
The progress of urban train projects have not met public expectation, said Deputy Prime Minister Hoang Trung Hai during a recent meeting to review the progress of urban train projects in Hanoi and Ho Chi Minh City.
The Deputy PM said there were a number of factors that contributed to the sluggish progress including slow land-site clearance, investors and project management boards' limited capability and a lack of cooperation between ministries, Government agencies and local authorities.
HCM City's metro Line 1 Ben Thanh-Suoi Tien, which started in August 2012, is estimated to have fallen behind schedule about two years. The date of completion is currently set for 2020.
HCM City's metro Line 2 Ben Thanh-Tham Luong, which began earlier this year in January was already two years behind schedule and is now set to be completed in 2019 after several changes were made to accommodate junctions with other metro lines such as Line 1, 3b, 5 and 6.
Similar delays were also seen with the Hanoi's Cat Linh-Ha Dong urban train project. The project, which was started in 2011, has been delayed a total of three times with the current date of completion pushed to the end of June 2016.
Major adjustments were made to these projects' investment cost. The Line 1 metro project's investment cost more than doubled from 1.09 billion USD in 2007 when it was approved to 2.49 billion USD in September 2011. The Line 2 project's investment cost also increased from 1.375 billion USD to more than 2 billion USD.
Most notable was the capital's infamous urban train project with the China Railway Sixth Group as EPC contractor. The investment cost for this project increased from 552 million USD in 2008 to 892 million USD in 2014 and suffered numerous delays and several deadly accidents.
Deputy PM Hai urged Hanoi and HCM City People's Committees to speed up land-site clearance and the Ministry and Transport to improve project management capacity as well as design.
The deputy PM said there was a need for special mechanisms that delegate decision making power to avoid unnecessary delays and bottlenecks.
In addition, the transport ministry was ordered to step up efforts on the preparation of urban train operations, regulation standards, technical maintenance as well as traffic and worker safety.-VNA
Quality must be given top priority at the ongoing construction of the Urban Railway Line 1 connecting Ben Thanh Market and Suoi Tien Theme Park, Secretary of Ho Chi Minh City’s Party Committee Le Thanh Hai said.
Transport Minister Dinh La Thang has said the construction of the Cat Linh-Ha Dong Railway Project should be speeded up so that commercial operations could begin by June 30, 2016.
Ho Chi Minh City’s Urban Civil Works Construction Investment Management Authority (UCCI) announced the Bus Rapid Transit (BRT) No 1 project on August 12.
Vietnamese Consul General in Fukuoka Vu Chi Mai highlighted the growing demand for Vietnamese workers in Kyushu, especially in Fukuoka, Oita, and Saga prefectures. Currently, the region employs about 35,000 Vietnamese manual workers and over 5,000 IT engineers.
In Vietnam’s case, she said, President Ho Chi Minh demonstrated his strategic vision by founding the revolutionary press a century ago. The late leader understood the press's role not only as a means to reflect the country’s realities but also as a powerful tool to strengthen national unity and inspire the resistance wars and national construction process.
In recent interviews granted to the Vietnam News Agency (VNA)'s reporters in Mexico, prominent figures reflected on the press’s legacy and its global influence.
VietnamPlus e-newspaper of the VNA clinched an A prize in the “Outstanding Press Product” category for its immersive 3D multimedia project, “Epic of Reunification,” a groundbreaking blend of storytelling and technology. The VNA won another A prize for its eye-catching exhibition booth.
Today, the press for foreign service has evolved into a distinct, irreplaceable force, bridging Vietnam with the world and portraying a nation that is stable, peace-loving, and fully integrated into the international community.
At a review conference held on June 21, Deputy Minister of Construction Nguyen Van Sinh praised the province’s scientific, coordinated, and flexible approach. He noted that the early completion reflects the strong commitment of local authorities, the business community, philanthropists, and residents in improving housing conditions for disadvantaged groups.
The VNA delegation, led by General Director Vu Viet Trang, actively participated in the event, engaging in both professional and diplomatic activities.
In the context where AI dominates and produces vast volumes of content, the only sustainable path forward for journalism is to focus on high-quality content and core values. Journalism must redefine its mission - not to report the fastest, but to provide the most profound and trustworthy value.
Granma and the VNA have great potential for cooperation, especially in sharing content regularly, so that VNA products are published on Granma platforms and vice versa, thereby helping Cuban and Vietnamese people access true information and gain a deep understanding of each other's country and people.
During his stay in China’s Guangzhou city from 1924 to 1927 to prepare for the establishment of a Communist Party to lead Vietnam’s revolution, President Ho Chi Minh founded “Thanh nien” newspaper and released its first issue on June 21, 1925.
Vietnam and Cambodia are hoped to strengthen their robust collaboration across various sectors, particularly in resolving remaining border issues to transform the border area into a zone of peace, friendship, cooperation, and development.
The strategic product, managed and operated by the Vietnam News Agency Digital Media Centre (VNA Media), is an official channel for popularising the Party and State’s information and documents as well as delivering mainstream and trustworthy news to both domestic and international audiences through various kinds of multimedia formats.
Since President Ho Chi Minh founded Thanh Nien (Young People) newspaper in 1925, the Vietnamese revolutionary press has become the voice of the people. During the resistance war against the colonialists, journalists took great personal risks to inspire patriotism and the will of rising up against foreign invaders.
The total investment exceeded 319 billion VND (12.2 million USD), including over 261 billion VND from the state budget and 57.5 billion VND mobilised from businesses, organisations, and individuals.
The Mekong Delta province of Tien Giang is intensifying efforts to combat illegal, unreported and unregulated (IUU) fishing as part of the country’s goal of having the European Commission’s “yellow card” warning lifted.
Throughout its 80-year history, the VNA has remained at the forefront of information dissemination. It has consistently delivered timely, accurate, and objective reports on both domestic and international events, serving the Party’s leadership, the State’s management, and the public’s demand for official news.
With strong support from local authorities, businesses, organisations, and residents, the province has successfully built or repaired 10,707 homes for disadvantaged households, including war veterans, families of martyrs, ethnic minority people, and low-income residents.
Throughout its resistance against colonialists and imperialists, Vietnam developed a revolutionary press that has served as a benchmark for just and legitimate causes worldwide.
Founded in 1842, the Vienna Philharmonic is regarded as a cultural ambassador of Austria, with prestigious conductors like Mahler and Karajan who shape its legacy. Its New Year’s Concert, broadcast to over 90 countries annually, stands as a global symbol of classical music excellence.